Read the formula behind the subtotal.

Calculate uniform slab volume, whole blocks and tile boxes using metres and editable INR rates.

EDIT THE ASSUMPTIONS

Measure. Allow. Round. Review.

Default quantities: 12.6 m³ concrete, 342 blocks and 23 boxes. Material-only examples, not complete construction quotations.

Concrete slab: quantity & material cost

Adjust the dimensions, allowance and example rate. Review the formula behind the result.

INR rates are illustrative editable inputs, not India market averages or supplier quotations. Review the actual product, allowance and delivery basis.

L × W × T
EXAMPLE MATERIAL SUBTOTAL
—

Build a detailed estimate in TB

This demo runs in your browser. Inputs are not saved or automatically transferred into a TB project.

KNOW THE BOUNDARY

One material quantity at a time.

Concrete

Uniform rectangular slab; use 0.15 m for 150 mm thickness. Not a design check.

Blocks

Nominal face dimensions are editable examples, not a standard Indian product claim.

Tiles

Area plus allowance divided by actual box coverage, rounded to full boxes.

Use project-specific inputs

Verify dimensions, product, allowance and quote scope before ordering. Rates are illustrative. Inputs stay in this browser without automatic saving or transfer.

Explore main TB calculators

BEFORE THE NEXT RENOVATION QUOTE OR MATERIAL ORDER

Make the next estimate easier to check.

Explore quantities, material purchasing, editable costs and resources in TrendyBuilders. Choose capacity for your own work or a team.

Make every allowance explainable.See plans